Golden 1 Center Construction Photos
View from West Sacramento with arena cranes in the air. Current work being done on the arena is installation of the second primary box truss at the arena high roof. Installation, bolting and welding of the arena high roof structure. Installation of high roof metal decking. Bolting and welding of steel frame exterior façade support “ladders.” Application of spray-applied fireproofing to
from LivingInUrbanSac http://ift.tt/1J7XfR7